The West Coast Expressway (E32), abbreviated WCE, is an interstate controlled-access highway running along the west coast of Peninsular Malaysia. The 233-kilometre (145-mile) expressway is currently under construction, with several sections open for public use. Once completed, the expressway will run between Changkat Jering, Perak and Banting, Selangor, following federal routes 5 and 60 for most of its route. The expressway will operate in three sections, with sections of federal route 5 completing the missing connections; these sections will be upgraded to limited-access roads. The expressway is expected to be fully completed by the end of 2025,[1][2] except for a 10 km stretch from Section 7B which is expected to be completed by June 2026.[3]
The expressway is being built by Konsortium Lebuhraya Pantai Barat. Approval was given by the government for the construction, which was to begin from 20 December 2013 and was to be completed within five years.[4] It originally was given route code E28 but later changed to E32, and E28 was used by Sultan Abdul Halim Muadzam Shah Bridge. The project was delayed and actual construction began in May 2014. Currently, a 31.5-kilometre (19.6 mi) segment between Kapar and Assam Jawa,[5] a 19-kilometre (12 mi) segment from Hutan Melintang to Teluk Intan[6] and a 45-kilometre (28 mi) segment from Lekir to Beruas[7] are opened to traffic.
Once the expressway is completed, it will be the fourth longest in Peninsular Malaysia, after the North-South Expressway Northern Route, the East Coast Expressway and the North-South Expressway Southern Route.
Overview
Construction of the expressway is divided into eleven packages. Works for the first five packages commenced in May 2014, of which three packages are in Selangor while the other two are in Perak. The stretches between Tanjung Karang to Hutan Melintang and Teluk Intan to Kampung Lekir are using the existing stretches of federal route 5, both of which are currently being upgraded. As a result, the expressway will consist of three non-contiguous stretches of controlled-access expressway (JKR R6), i.e. from Banting to Tanjung Karang, Hutan Melintang to Teluk Intan and Lekir to Changkat Jering while the two stretches on federal route 5 are partial access highways (JKR R5) featuring grade-separated interchanges at major junctions, left-in/left-out junctions and at-grade U-Turns.
A spur link from Changkat Keruing to Siputeh (near Ipoh) in Perak which will be connected via an interchange with the main link is also in the plan. Construction of the spur link is however deferred. The spur link will consist of a controlled-access expressway (JKR R6) stretch from Changkat Keruing to Parit while the stretch between Parit to Siputeh will use the existing stretch of federal route 73 will be similarly upgraded like the two federal route 5 stretches of the main link package has been awarded to Gedeihen Engineering Sdn Bhd. The controlled-access expressway stretches will use a closed toll system like the North–South Expressway. Toll collection has started at all opened stretches of the expressway. The stretches on existing federal roads will remain toll-free.
Progress updates on construction of the expressway is updated monthly here.
On 25 May 2014, the construction of the expressway began. The groundbreaking ceremony for the new expressway was held near the Teluk Intan interchange in Teluk Intan, Perak.
Five interchanges (sections 4–5, 8–10) were expected to be opened in time for Eid al-Fitr in 2019[8] but a burst water pipe on 5 May 2019 delayed the opening of sections 4–5.[9]
On 31 May 2019, section 8 between Hutan Melintang and Teluk Intan in Perak was opened to traffic. The opening ceremony was officiated by the Deputy Minister of Works, Mohd. Anuar Tahir.[6] This followed by the opening of sections 9 and 10 between Lekir and Beruas, also in Perak on 23 September 2019 and officiated by Works Ministry secretary-general Datuk Dr Syed Omar Sharifuddin Syed Ikhsan.[7] The first section to open in Selangor was section 5 between Kapar and Bukit Raja and officiated by Malaysian Highway Authority director-general Datuk Mohd Shuhaimi Hassan. This stretch was opened to public on 10 December 2019.[5]
Land acquisition issues and alignment changes causing delay of the construction of section 7 (Assam Jawa–Tanjung Karang),[8] which will be completed by 2024 along with section 11 (Beruas–Taiping South).[10][11]
As of 21 November 2023, section 6 (Kapar – Assam Jawa) is opened to traffic along which steady progress being made at sections 7 and 11, with are the most integral sections of the expressway to be completed to ease traffic congestion at Tanjung Karang and along FT 60, especially during festive seasons.[12]
WCE group has the first right of refusal for Section 12 (Siputeh – Segari) which will cost RM600 million with 41 km stretch. There is a plan to extend the expressway all the way to Penang if it is feasible.[10]
There's also a proposal by the Johorean state government to extend the WCE to Melaka, Pontian, and Iskandar Puteri from Banting. If it is feasible, WCE will be the alternative route to the North South Expressway from Johor Bahru to Taiping.[13]
Route background
![](../I/WCE_highway_from_Sungai_Rasau.jpg.webp)
![](../I/WCE_Changkat_Jering_IC_(220806).jpg.webp)
![](../I/Airasia_-_Aerial_photographs_of_WCE_Terong_(230815)_01_(cropped).jpg.webp)
The northern terminus of the expressway will be located at Changkat Jering on the North–South Expressway Northern Route. The southern terminus will be located at Banting on Federal Route 31. The expressway will have interchanges to Trong, Beruas, Changkat Cermin, Sitiawan, Lekir, Teluk Intan, Hutan Melintang, Sabak Bernam, Sungai Besar, Sekinchan, Tanjung Karang, Kuala Lumpur–Kuala Selangor Expressway at Assam Jawa, Kapar, New North Klang Straits Bypass, New Klang Valley Expressway at Bukit Raja, Federal Highway at Klang, Sri Andalas, Shah Alam Expressway near Jalan Kebun and South Klang Valley Expressway.
12 sites have been identified as rest and services area with each area will have 2 petrol stations.[10]
Tolls
The expressway implements closed toll system where rates are calculated between entry and exit of the expressway. However toll collections are not implemented in Federal Route 5 upgraded sections, making the closed toll section divided into three sections, including the short section of Hutan Melintang - Teluk Intan as well where vehicles still need to go through entry and exit tolls despite not having interchanges in between.
As for now toll collection has begun in all the opened sections.
Toll rates
Class | Types of Vehicles | Rate (in Malaysian ringgit RM) |
---|---|---|
0 | Motorcycles | Free |
1 | Vehicles with 2 axles and 3 or 4 wheels excluding taxis | RM 2.90 |
2 | Vehicles with 2 axles and 5 or 6 wheels excluding buses | RM 5.80 |
3 | Vehicles with 3 or more axles | RM 8.70 |
4 | Taxis | RM 1.50 |
5 | Buses | RM 2.20 |
Junction list
State | District | km | Interchange | Name | Destination | Note |
---|---|---|---|---|---|---|
Perak | Larut, Matang & Selama | 3238 | Taiping Selatan | ![]()
|
Under construction. | |
Taiping Selatan Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system (under construction) | ||||||
3237 | Trong | ![]() |
Trumpet interchange. Under construction | |||
Sg. Nyior Rest and Service Area (under construction; both directions; separated) | ||||||
Manjung | 241.63 | 3235 | Beruas | ![]() |
Trumpet interchange.
Closed toll collection system start/end temporary here. | |
222.55 | 3233 | Changkat Cermin | ![]() |
Trumpet interchange | ||
216.5 | Ayer Tawar Rest and Service Area (under construction; northbound)
West Coast Expressway North Region Office (northbound) | |||||
210.1 | 3232 | Sitiawan Utara | ![]()
|
Trumpet interchange | ||
208.0 | Sungai Wangi Rest and Service Area (under construction; southbound) | |||||
202.89 | 3231 | Sitiawan | ![]()
|
Trumpet interchange | ||
197.71 | Lekir Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system | |||||
196.24 | 3230 | Lekir | ![]() |
Diamond Interchange | ||
193.59 | Expressway ![]() ![]() Federal Route | |||||
Batu 14 Lekir | ![]() |
LiLO interchange, entry/exit only for northbound traffic | ||||
Kampung Kayan | Kampung Kayan | LiLO Interchange, entry/exit only for northbound traffic | ||||
Perak Tengah | Bagan Datuk Bridge (Sultan Nazrin Shah Bridge) | ![]() |
LiLO Interchange, entry/exit only for northbound traffic | |||
Jalan Trans Perak | ![]() |
Directional T-junction with traffic lights | ||||
Jalan Kota Setia | ![]() |
LiLO Interchange, entry/exit only for northbound traffic | ||||
Jalan Bota Kiri | ![]() |
LiLO Interchange, entry/exit only for southbound traffic | ||||
Hilir Perak | Sungai Rubana | Kampung Sungai Rubana | ||||
Tanjung Sari | Tapak Semenang, Tanjung Sari, Teluk Bharu | LiLO Interchange, entry/exit only for northbound traffic | ||||
Sultan Yusuf Bridge | ||||||
162.07 | Federal Route ![]() Expressway | |||||
3223 | Teluk Intan | ![]()
|
Diamond interchange. | |||
Teluk Intan Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system | ||||||
Teluk Intan Rest and Service Area (under construction; both directions; separated) | ||||||
Bagan Datuk | Hutan Melintang Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system | |||||
3222 | Hutan Melintang | ![]()
|
Diamond interchange. | |||
143.99 | Expressway ![]() ![]() Federal Route | |||||
Perak–Selangor border | Bernam River Bridge | |||||
Selangor | Sabak Bernam | Sabak Bernam | ![]() |
Diamond interchange | ||
Sungai Air Tawar | ![]() |
Diamond interchange | ||||
Sungai Besar | ![]() |
Diamond interchange | ||||
Sungai Panjang | ![]() |
Diamond interchange | ||||
Sekinchan | Jalan Bahagia – Sekinchan | Diamond interchange | ||||
Kuala Selangor | Federal Route ![]() Expressway | |||||
3212 | Tanjung Karang | ![]() |
Under construction. Diamond interchange | |||
Tanjung Karang Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system (under construction) | ||||||
3210 | Assam Jawa | ![]()
|
Trumpet interchange | |||
Klang | Bukit Kapar Rest and Service Area (under construction; both directions; separated) | |||||
39.95 | 3208 | Kapar / Bandar Bukit Raja North | ![]()
|
Trumpet interchange | ||
34.55 | 3207 | Bandar Bukit Raja South / (NNKSB) 2 | 3207A
3207B 3207C |
Half cloverleaf interchange; exit from northbound only | ||
3206 | Sungai Rasau (Federal Highway) | ![]() ![]() |
Under construction; exit from Banting / southbound only | |||
3205 | Sri Andalas | ![]() |
Under construction | |||
3204 | Shah Alam Expressway (KESAS) | ![]() ![]() ![]() |
Under construction; trumpet interchange | |||
Kuala Langat | 3203 | South Klang Valley Expressway (SKVE) | ![]() ![]() ![]() |
Under construction; trumpet interchange | ||
Banting Toll Plaza Touch 'n Go SmartTAG MyRFID Start/End closed toll collection system (under construction) | ||||||
3201 | Banting | ![]() ![]() |
Under construction; trumpet interchange |
References
- ↑ "Hot spots coming up along WCE". Edgeprop.my. Retrieved 19 December 2019.
- ↑ TAHIR, MOHD IZZATUL IZUAN (6 December 2022). "Lebuhraya Taiping-Banting beroperasi sepenuhnya 2025". Sinar Harian (in Malay). Retrieved 1 June 2023.
- ↑ "Bumpy path to profitability | The Star". www.thestar.com.my. Retrieved 20 August 2020.
- ↑ http://www.wce.com.my/media-updates/New-beginning-for-KEuro
- 1 2 Chan, Dawn (1 December 2019). "West Coast Expressway opens Section 5 stretch to traffic tonight". NST Online. Retrieved 19 December 2019.
- 1 2 Arif, Zahratulhayat Mat (3 May 2019). "Section 8 of West Coast Expressway opens today". NST Online. Retrieved 19 December 2019.
- 1 2 Bernama (2 September 2019). "Sections 9, 10 of WCE now open". NST Online. Retrieved 19 December 2019.
- 1 2 "West Coast Expressway – Media Updates – WCE back in the spotlight". wce.com.my. Retrieved 19 December 2019.
- ↑ Thiagarajan, Tara (9 May 2019). "Photos Show Extent Of Damage to Collapsed Expressway That Caused Unexpected Water Shortage in Klang – WORLD OF BUZZ". worldofbuzz.com/. Retrieved 19 December 2019.
- 1 2 3 "In high gear to complete 233km West Coast Expressway | The Star Online". The Star. Malaysia. Retrieved 14 January 2020.
- ↑ "WCE highway completion delayed to 2024 | The Malaysian Reserve". The Malaysian Reserve. Malaysia. Retrieved 3 November 2020.
- ↑ BERNAMA (20 November 2023). "WCE SECTION 6 OPENS AT MIDNIGHT, NO TOLL UNTIL JAN 2, 2024". BERNAMA. Retrieved 20 November 2023.
- ↑ "Rancangan Struktur Negeri Johor 2030 (RSNJ 2030)" (PDF). PLANMalaysia. 1 (1): 78. 26 March 2020 – via Government of Malaysia, Ministry of Housing and Local Government (Kementerian Perumahan dan Kerajaan Tempatan; KPKT).